SWPPP Requirements in Pennsylvania

Disturbing an acre or more in Pennsylvania means an E&S Plan before you break ground. Here is what the state requires — permit, filing, and inspections — and how to be inspection-ready in minutes.

Compliance SnapshotPA
Permitting authorityPennsylvania Department of Environmental Protection (DEP), Bureau of Clean Water
General permitPAG-02
Plan nameE&S Plan
Engineer stampNot required
CertificationQualified site inspector
1 ac
Disturbance threshold
1× week
Routine inspection cycle
0.25 ″
Rain that triggers inspection
PAG-02
NPDES general permit

Who needs an E&S Plan in Pennsylvania?

Any construction project that disturbs one acre or more — or is part of a larger common plan of development reaching one acre — needs an E&S Plan under Pennsylvania permit PAG-02.

Pennsylvania runs its own delegated stormwater program. Operators obtain coverage from Pennsylvania Department of Environmental Protection (DEP), Bureau of Clean Water under PAG-02 NPDES General Permit for Discharges of Stormwater Associated with Construction Activities (PAG-02), not directly from the EPA. A small subdivision, a solar pad, and a road-widening project all clear the same one-acre line.

Pennsylvania adds requirements worth flagging early: Approved Chapter 102 Erosion and Sediment Control (E&S) Plan meeting 25 Pa. Code § 102.4(b) and Post-Construction Stormwater Management (PCSM) Plan meeting § 102.8, implemented at all times (Part C V–VI); NOI package submitted to the County Conservation District (or DEP regional office) at least 60 days before the planned start; no discharge until written approval of coverage (NOI Requirements; Authorization conditions 1–2); Record a legal instrument disclosing planned PCSM SCMs with the Recorder of Deeds before the pre-construction meeting (Part C II); Pre-construction meeting with at least seven days’ notice to invitees, unless waived in writing (Part C III); Notify DEP/CCD at least three days before bulk earth disturbance once perimeter sediment controls are installed (Part C IV); Preparedness, Prevention, and Contingency (PPC) Plan when polluting materials are on site (Part A I.B.4.c; Part C VIII); Annual Report to DEP/CCD by December 7 for the October–September period (Part A III.D.1); Discharges to HQ or EV waters, and to waters impaired for sediment or nutrients without a non-discharge alternative or ABACT BMPs, are not eligible (Discharges Not Authorized, items 9, 14, 15).

What the plan must contain

A Pennsylvania E&S Planis the site's compliance binder — the document an inspector opens first. It documents:

  1. 1Site & project descriptionTotal and disturbed acreage, soils, slopes, and the sequence of construction.
  2. 2Receiving waters & discharge pointsWhere stormwater leaves the site and the waterbodies it reaches.
  3. 3Erosion & sediment control BMPsSilt fence, stabilized entrances, inlet protection, and stabilization measures.
  4. 4Inspection schedule & recordsDated, signed inspection logs and the corrective actions taken.
  5. 5Operator certificationThe E&S Plan is signed by the legally responsible party before work begins.

Required and conditional BMPs

Best management practiceCategoryStatus
Perimeter silt fence / sediment barrierSediment controlRequired
Stabilized construction entranceTracking controlRequired
Storm drain inlet protectionSediment controlRequired
Soil stabilization (seeding, mulch, blankets)Erosion controlRequired
Concrete washout containmentGood housekeepingRequired
Sediment basin or trapSediment controlConditional
Dewatering / turbidity controlsPollution preventionConditional

Filing your Notice of Intent

Submit the PAG-02 NOI package (3800-PM-BCW0405b with the NOI checklist and fees) to the County Conservation District for the county (DEP regional office for Forest and Philadelphia counties and multi-county projects) at least 60 days before construction; DEP’s ePermitting system accepts PAG-02 NOIs electronically on a voluntary basis (NOI Requirements; fact sheet).

A Notice of Termination closes coverage once the site reaches final stabilization. Keeping the E&S Plan and its inspection records on site is what keeps a project clear of stop-work orders.

Inspection requirements

Inspect at least once every calendar week and within 24 hours after the conclusion of a storm producing 0.25 inch of rain or more over a 24-hour period (also within 24 hours after snowmelt sufficient to cause a discharge, and a corrective action inspection whenever a deficiency in implementing the E&S or PCSM Plan is observed; throughout construction until DEP/CCD approves the Notice of Termination) (PAG-02 Part A III.C.1). Document each inspection on DEP’s Chapter 102 Visual Site Inspection Report (3800-FM-BCW0271d) or an equivalent form, with date- and time-stamped color photographs of BMPs and SCMs at least monthly and whenever deficiencies are found (PAG-02 Part A III.C.1.a). Every inspection is dated and signed, and any failed control is corrected before the next storm.

TriggerRequirement
RoutineAt least once every calendar week and within 24 hours after the conclusion of a storm producing 0.25 inch of rain or more over a 24-hour period (also within 24 hours after snowmelt sufficient to cause a discharge, and a corrective action inspection whenever a deficiency in implementing the E&S or PCSM Plan is observed; throughout construction until DEP/CCD approves the Notice of Termination)

How Pennsylvania differs from the federal permit

PennsylvaniaFederal (EPA)
AuthorityPennsylvania Department of Environmental Protection (DEP), Bureau of Clean WaterU.S. EPA
PermitPAG-02EPA CGP
Disturbance threshold1 acre1 acre
Plan nameE&S PlanSWPPP

Because Pennsylvania administers its own program, the federal EPA Construction General Permit does not apply directly here — the state permit governs. Sites inside a regulated municipal storm sewer system may carry additional local ordinance requirements on top of the state permit.

Frequently asked questions

Does Pennsylvania require an engineer to prepare the E&S Plan?+

No. Pennsylvania does not require a licensed PE stamp on a construction E&S Plan statewide. The operator certifies the plan; engineer review is optional for complex sites.

What is the disturbance threshold in Pennsylvania?+

One acre — including sites under an acre that are part of a larger common plan of development totaling one acre or more.

How often must inspections happen in Pennsylvania?+

Inspect at least once every calendar week and within 24 hours after the conclusion of a storm producing 0.25 inch of rain or more over a 24-hour period (also within 24 hours after snowmelt sufficient to cause a discharge, and a corrective action inspection whenever a deficiency in implementing the E&S or PCSM Plan is observed; throughout construction until DEP/CCD approves the Notice of Termination) (PAG-02 Part A III.C.1). Document each inspection on DEP’s Chapter 102 Visual Site Inspection Report (3800-FM-BCW0271d) or an equivalent form, with date- and time-stamped color photographs of BMPs and SCMs at least monthly and whenever deficiencies are found (PAG-02 Part A III.C.1.a).

Is an E&S Plan the same as a SWPPP?+

Yes. Pennsylvania uses the term "E&S Plan" for what other states call a SWPPP — the same plan and the same requirements.

What is a Qualified site inspector and does my site need one?+

Since 2025-12-08, site inspections and Visual Site Inspection Reports are completed by qualified personnel: DEP Clean Water Academy Qualified Site Inspector training (renewed every two years), an active CPESC or CESSWI certification, or equivalent qualifications approved in writing by DEP/CCD (Part A III.C.1.c).

Pennsylvania-ready in minutes

Siltworks fills in your site data automatically, applies the Pennsylvania requirements, and hands you an inspection-ready E&S Plan — at 70–90% less than a consultant.

Requirements summarized from the publicly available PAG-02 NPDES General Permit for Discharges of Stormwater Associated with Construction Activities (PAG-02) for planning purposes. The operator must review and certify every E&S Plan before use.